Daily Reservoir and Pass-Thru Status Report
June 19, 2021
Reservoir Supply (AcFt); Stream Flow (AcFt); Evaporation (AcFt); Elevation (Ft); Rainfall (Inches); Temperature (°F); Gage Height (Ft MSL)
RESERVOIR STATISTICS
Effective June 24, 2017, updated total reservor capacities for Choke Canyon Reservoir (2012 TWDB Volumetric Survey) and
Lake Corpus Christi (2016 TWDB Volumetric Survey) are being reflected in the Daily Reservoir System and Pass-Thru Status Report
  Choke Canyon Reservoir Lake Corpus Christi CCR/LCC Combined Lake Texana
Date Elevation Volume % Capacity Elevation Volume % Capacity Volume % Capacity Elevation Volume % Capacity
FULL 220.5 662,821 100% 94.0 256,339 100% 919,160 100% 44.0 161,085 100%
06/19/2021 204.4 325,645 49.1% 91.9 216,174 84.3% 541,819 58.9% 44.0 161,085 100.0%
06/18/2021 204.5 327,318 49.4% 91.9 216,174 84.3% 543,492 59.1% 44.0 161,085 100.0%
05/19/2021 199.5 249,001 37.6% 87.0 134,734 52.6% 383,735 41.7% 44.0 161,085 100.0%
06/19/2020 201.5 278,904 42.1% 89.5 173,834 67.8% 452,738 49.3% 43.4 155,551 96.6%
LAKE TEXANA WATER SUPPLY*
* The split between Non-Interruptible and Interruptible amounts are updated monthly, usually the first working day of the month, so they reflect the total and remaining amounts as of the end of the previous month
Date Daily Intake MTD Non-Interuptible Interruptible
May YTD Remaining May YTD Remaining
06/18/2021 121 2,734 0 6,497 24,943 3,684 8,184 3,816
COLORADO RIVER WATER SUPPLY (CRWT)
Date Daily
Intake
MTD YTD Daily Flow MTD Flow Date Time Gage Height
06/18/2021 68 308 5,244 2,322 302,316 06/19/2021 7:15 AM 9.93
WEATHER RELATED INFORMATION
  Choke Canyon Reservoir Lake Corpus Christi CCR/LCC Combined
  06/18/2021 MTD YTD 06/18/2021 MTD YTD 06/18/2021 MTD YTD
Air Temp 93     92        
Evaporation 311 5,176 29,010 377 4,491 26,107 688 9,667 55,117
Rainfall 0.00 1.61 16.5 0.00 2.49 17.08      
Stream Flows
Gauging Station 06/18/2021 MTD
NTRT Nueces River at Three Rivers, Texas 353 60,967
NRTT Nueces River at Tilden, Texas 99 20,902
FRTT Frio River at Tilden, Texas 24 34,882
SMTT San Miguel Creek at Tilden, Texas 6 7,628
ARWT Atascosa River at Whitsett, Texas 65 41,024
CCR Release from Choke Canyon Reservoir 58 824
NRMT Nueces River at Mathis, Texas (La Fruta Bridge) 705 8,365
NCAT Nueces River at Calallen, Texas 270 5,078
RBP Rincon Bayou Pipeline 233 3,275
Reservoir InFlow
Computed as: (NTRT+FRTT+SMTT)-Release from Choke Canyon 326 102,653
ESTUARY INFLOWS AND PASSTHRU REQUIREMENTS
Target Passthru Monthly Target 23,000   23,000
Salinity Relief Credit 0 Effective  
Credit / -Deficit From Previous Month Date Deficit Satisfied   619
Return Flow Credit Effective   500
Required Passthru Monthly Target 23,000   23,000
Reservoir Inflow 102,653
Estuary Inflows (NCAT + RBP) 8,354
Passthru Surplus / -Deficit -13,527
Report Generated 6/19/2021 at 8:38:12 AM